Residents of the North East Gonja District in the Savannah Region continue to face challenges accessing quality healthcare, secondary education and public services as several key development projects remain incomplete.
The situation has also affected efforts to provide decent accommodation for nurses and teachers posted to rural communities, making the delivery of essential public services more challenging.
According to the Daily Graphic newspaper, monitored by Angelonline on Tuesday, November 17, the affected projects include an Agenda 111 hospital, a Community Day Senior High School E-Block, a district assembly office complex and a 20-unit nurses’ and teachers’ quarters.
The Member of Parliament (MP) for the area, Alhassan Mumuni, brought the situation to light during a tour of the projects to assess their progress and identify challenges delaying their completion.
The district assembly office complex, which was initiated in 2023, is approximately 90 per cent complete, while the 20-unit residential facility for nurses and teachers, also started in the same year, has recorded 40 per cent progress.
The Agenda 111 hospital project, which commenced in 2024, is about 70 per cent complete, while the Community Day Senior High School E-Block, started in 2015, has recorded only five per cent progress.
Addressing the challenges confronting healthcare delivery, Mr Mumuni said the absence of a district hospital had compelled residents seeking specialised medical care to travel to Salaga and Tamale.
He explained that patients referred from Community-based Health Planning and Services (CHPS) compounds and health centres often encountered difficulties accessing essential treatment due to the long distances involved.
The MP therefore urged the Ministry of Health to fast-track the hospital project and consider it among the first 10 Agenda 111 facilities to be completed nationwide.
On education, he expressed concern over the district’s lack of a senior high school, which he said had forced students to travel outside the area to pursue secondary education.
He said the District Assembly had provided some infrastructure towards establishing a senior high school and was making efforts to secure the completion of the stalled E-Block.
Mr Mumuni also called on the Minister of Education to intervene to facilitate the project’s completion.
Touching on the district assembly office complex, the MP said its completion would create the needed administrative space to attract more government institutions and improve service delivery.
He revealed that attempts to secure the establishment of offices for agencies such as the National Health Insurance Scheme (NHIS), Environmental Protection Agency (EPA) and Forestry Commission had been unsuccessful due to inadequate office accommodation.
“I have moved from one agency to the other to seek officers, and what they demand is office space. Once you have office space, we will get you staff,” he said.
He noted that the absence of these institutions had undermined development efforts, particularly in enforcing environmental regulations and safeguarding the district’s natural resources.
As part of the visit, the MP donated a printer, a laptop and a motorbike to the National Disaster Management Organisation (NADMO) to strengthen its operational capacity.
Meanwhile, the District Chief Executive (DCE), Ewuntomah Abdul Mumin, disclosed that the government had directed the assembly to utilise its legacy funds to complete the district assembly office complex.
He said the project had been re-awarded, with completion expected within six months, although the contractor had indicated that the work could be finished in three months.
“We have committed some funds to complete the assembly office complex, but the contractor is yet to receive the money and return to work,” he said.
Source: Abigail Ekua Arhin